As of February 4, 2019 the construction of Mason Clinic will impact patient drop offs, parking and the flow of traffic.


Notice of Utility Work - Patient Parking and Drop Offs Updates for February 4 Thru March 4, 2019

2/4/19 - 2/6/19

A section of drive lane at the South Main Entrance will be closed during day hours. Traffic will be directed by flagger during the day. Traffic will be restored at night.

2/9/2019

Patient drop-off location will be relocated on Saturday only.

2/6/19 - 2/22/19

Removal of existing ADA parking stalls. 5 ADA parking stalls will be available.

Patient-Drop-Off-Location-Image-Feb-Mar-2019.jpg#asset:8134

02/25/19 - 03/1/2019

Work related to the sanitary sewer connection work will continue and asphalt demolition for new entrance driveway at South Main Entrance of MGH will begin and access point for patient drop-offs will be changed temporarily.

Patient drop-off location will be relocated on Monday, 2/25 and through Friday, March 1. See above image to find drop-off location.

Parking lot access will be blocked west of new driveway entrance at MGH's South Main Entrance. Two-way traffic will be maintained at existing driveway.

02/26/19 - 03/04/19

Asphalt Paving for New Entrance Driveway at MGH's South Main Entrance.

Parking lot access will be blocked west of new driveway entrance. Two-way traffic will be maintained from existing driveway.

03/05/19 - 03/11/19

The new South Main Entrance driveway will be open. Pedestrian traffic will be re-routed to MGH's North Emergency Entrance.